测绘通报 ›› 2023, Vol. 0 ›› Issue (2): 172-176,181.doi: 10.13474/j.cnki.11-2246.2023.0060

• 测绘地理信息技术应用案例 • 上一篇    下一篇

北京新机场线长距离掘进贯通测量精度控制

朱水鹏   

  1. 北京市政建设集团有限责任公司第四工程处, 北京 100049
  • 收稿日期:2022-10-31 发布日期:2023-03-01
  • 作者简介:朱水鹏(1986-),男,工程师,主要从事地下工程、城市轨道交通建设等领域的测量技术管理研究工作。E-mail:327873933@qq.com

The precision control of long distance tunneling through survey for Beijing new airport line

ZHU Shuipeng   

  1. China Railway Construction Group Real Estate Co., Ltd., Beijing 100049, China
  • Received:2022-10-31 Published:2023-03-01

摘要: 近几年,随着经济的飞速发展,城市轨道交通也加快了提速的步伐,各种型号的大直径盾构机相继投入到地铁隧道建设中。大直径盾构机相较于传统盾构机型而言,具有机体庞大、成型环片自重大、对地层的扰动性大等特点,对地下控制点的稳定性有较大影响。盾构法施工隧道一次成型,隧道内控制导线一般采用支导线或环形导线的形式,误差累积较大,尤其是长距离隧道对测量精度控制要求更高。因此,大直径盾构长距离隧道施工中,保证盾构精准贯通是对测量控制技术的新考验。本文以北京轨道交通新机场线一期工程北航站楼(不含)-磁各庄(不含)盾构段区间实际施工为例,简要叙述了测量工作的控制流程和关注点,重点阐述、剖析联系测量精度控制和隧道内测量各个细节的精度把控等方面,为在大直径盾构机长距离施工中测量精度的提高提供参考。

关键词: 大直径盾构, 长距离, 控制测量, 提高精度

Abstract: In recent years, with the rapid development of economy, urban rail transit also has accelerated the pace of speed increase, and various types of large diameter shield machines have been put into the construction of subway tunnels. Compared with the traditional shield machine, the large-diameter shield machine has the characteristics of large body, heavy self weight of formed ring, large disturbance to the stratum, and so on, which has a great impact on the stability of underground control points. The shield method is used to construct the tunnel at one time. The control wire in the tunnel is generally in the form of branch wire or ring wire, with large error accumulation. Especially for long distance tunnels, the measurement accuracy control is required to be higher. Therefore, in the construction of large-diameter shield long-distance tunnel, how to ensure the accurate penetration of the shield is a new test of the measurement control technology. Taking the first phase project of the new airport line of Beijing rail transit as an example, this paper briefly describes the control process and concerns of the survey work during the actual construction of the shield section of Beihang station building (excluding)-Cigezhuang (excluding), and focuses on the precision control of the contact survey and the precision control of each detail of the survey in the tunnel. It provides reference for improving measurement accuracy in long-distance construction of large diameter shield machine.

Key words: large diameter shield, long distance, control measurement, improve accuracy