Abstract: As a non-excavation construction method, pipe jacking is widely used because of saving resources. However, pipe jacking construction will also cause soil deformation around the pipe, which will cause the soil to move and cause ground settlement. Therefore, an effective and accurate settlement monitoring method is indispensable. According to the general rule of pipe jacking construction, the high-precision Trimble S9/S9 HP total station and the differential presure static level are used to set up the monitoring plan for the settlement in this paper. According to the observation results, this kind of scheme can effectively and accurately reflect the settlement situation, which has great significance in practical production and can be promoted and used.
Key words: pipe jacking construction, settlement monitoring, differential pressure static level, Trimble S9/S9 HP total station, non-excavation
CLC Number:
P23
SONG Zhonghua, TIAN Hui, SONG Shuai. Application of Trimble S9/S9 HP total station in precision settlement monitoring of railway pipe jacking construction subgrade[J]. Bulletin of Surveying and Mapping, 2020, 0(6): 153-155.
0 / / Recommend
Add to citation manager EndNote|Reference Manager|ProCite|BibTeX|RefWorks
URL: http://tb.chinasmp.com/EN/10.13474/j.cnki.11-2246.2020.0200
http://tb.chinasmp.com/EN/Y2020/V0/I6/153